![]() ![]() I created this project planner primarily to experiment with different ways of showing the Planned vs. If you want to use the Days column but enter the Start and End dates, then you can calculate the Days using a formula: = end_date- start_date+1. The "-1" is included because a task is assumed to begin the morning of a day and end in the evening, such that a 1-day task is represented as having the same Start and End date. However, it is usually convenient to define the End date by entering the duration in Days, so you can use a formula for the End Date such as = start_date+ days-1. ![]() The gantt chart in this project planner spreadsheet relies only on the Start and End date columns, so you could delete the Days columns.